building period based on a shearwall system
my question is for a dyanmic design using etabs i have dynamic period of 4.5 s  with 70% mass participation. if i use the alternate equation for building fundamental period for a shear wall buildings it gives me a period of 2.7 secconds and with a 1.4 factor that allows me to base my base shear coefficient on a period t=1.4 x 2.7= 3.78 seconds. alternatively if i use the other fundemental equation for period which is t=ctx(hn)^3/4 then i get a period that is 1.23 seconds or with the upper limit of 1.4 it comes in at 1.72 which is significantly different than 3.78 seconds.
two quesitons:
1. from what i have seen in asce 7-02 the alteranate peroid equations is allowed...commnets?
2. it appears that the alternate period equation is only for planer shearwalls and not walls that have flanges,t's or form a tube,ect, is the use of this equations accpetable if the walls are anything but planer?
thanks for the input
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|小黑屋|几何尺寸与公差论坛

GMT+8, 2025-1-12 06:30 , Processed in 0.034496 second(s), 19 queries .

Powered by Discuz! X3.4 Licensed

© 2001-2023 Discuz! Team.

快速回复 返回顶部 返回列表