lpile question
i am getting very large negative deflections for my pier lpile runs when using a pinned head connection (hpile will be encased in concrete approx. 22ft above ground surface).  can i use a fixed-head connection in this case.  if i use a pinned head connection, what could i use as a control option, how much deflection should i allow?   
(hpile will be encased in concrete approx. 22ftfff"> above ground surface)
how could it be pinned?
how much is the embedment length of the pile (into concrete)?
embedment 22 ft into concrete.   
sorry, i was unclear, it will be encased in the concrete from ground surface to 22 ft above ground surface.  so fixed head then?
fixed.
reason: the angle between the pile and the bottom face of the mass concrete will stay constant.
thank you very much
my pleasure, if that solves your problem.
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|小黑屋|几何尺寸与公差论坛

GMT+8, 2025-1-20 05:37 , Processed in 0.034438 second(s), 20 queries .

Powered by Discuz! X3.4 Licensed

© 2001-2023 Discuz! Team.

快速回复 返回顶部 返回列表