minimum dead load for uplift on wood roof trusses
i have a roof system with a total dead load including asphalt shingles, batten insulation, 5/8" sheathing & felt, ceiling, mech. of 20 psf. is 13 psf minimum dead load a good number to use for component & cladding uplift or .6 times 16 psf(total-mechanical number of 4 psf = 10 psf? is the .6 multiplier necessary? thank you.
find a job or post a job opening
i normally use 15psf for dead load of wood roofs. you'll still need to look at the
0.6d+w combination though. |
|