question regarding prequalified smf reduced beam section connection design:

according to seismic provisions section 9.6, in the equation for mpb for prequalified rbs includes 1.1ry*fyb*zrbs, however, in the aisc 358 section 5.4, it directs you to eq 5.8-5 where mpr = cpr*ry*fy*ze.

why are these two equatons using different values, 1.1 vs. cpr?

check out our whitepaper library.
per fema 350, june 2000, commentary section 3.2.4(see link below), in calculating mpr the coefficent 1.1 was used in the 1997 aisc seismic provisions, however, fema testing determined that for most connection types, the peak moment developed is higher than using 1.1, therefore the cpr factor was developed, limited by 1.2.
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|小黑屋|几何尺寸与公差论坛

GMT+8, 2025-1-17 07:24 , Processed in 0.036631 second(s), 19 queries .

Powered by Discuz! X3.4 Licensed

© 2001-2023 Discuz! Team.

快速回复 返回顶部 返回列表