too many requests for calculations
good afternoon all,
i'm looking for advice/comments centering around what i feel are excessive requests by an owner for backup calculations.
i read through jae's
speaking of calculations i was talking to my boss yesterday about the need to continue with calculation programs (mathematica and basic) to support our current product design.  he looked at me with puzzled expression and asked, doesn't autocad do that.  it seems to me that things that were clear to most of us and understood years ago, are not necessarily understood today.
i was involved in a project where i was having difficulty getting my conveyor load drawings accepted by the general contractor.  it was really simple statics but the reviewer had his own way of calcualting reactions.  it took a meeting wtih me and other managers from my company along with the project owners, gc, design consultants, project managers, and other specialists to resolve this issue.  while it turned out in my favor it took people at the highest level of the project to make it happen.  
in your case it might be important how your scope of work is worded along with what this "usually" means.
regards,
-mikere
it seems you have one of those scope creep problems - the bane of our industry...
you may have to swallow it on this job, but i'll bet in the future you'll include contract language to combat this.  if this was an extra in the contract and you were hitting him for 10 hours or more for each small change, he may have reconsidered.  however, even if the client doesn't reconsider on future jobs, then you provide the service and get paid for it.
having been in the profession for about 35 years, we have seen our calcs for a particular project balloon from several pages to several volumes. alot of it has to do with the advent of computer programs, but some of it has to do with some unknown momentum that seems to require every little thing to be calculated.
this momentum may be a result of stricter oversite by inexperienced managers who do not know what actually is required. it also has to do with everyone's exposure to increased liability.
i don't know what the solution is other than contractural language that allows you to get paid for your additional effort.
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|小黑屋|几何尺寸与公差论坛

GMT+8, 2025-1-11 19:20 , Processed in 0.038697 second(s), 19 queries .

Powered by Discuz! X3.4 Licensed

© 2001-2023 Discuz! Team.

快速回复 返回顶部 返回列表