默认 simultaneous requiremen

"simultaneous requirement"?
i have a customer drawing with some holes controlled with compound true position callouts. under the true position block is "simultaneous requirement". what does this mean?
i understand that both parts of the compound true position are simultaneous requirements, but does this need to be spelled out separately, or is this just a redundancy?
i have never seen this before. seems redundant to me. redundancy is very common.
chris
systems analyst, i.s.
solidworks/pdmworks 05
autocad 06
thanks, chris. that is what i am thinking, but wanted to be sure that i wasn't missing something.
it sometimes seems that there are as many ways to interpret the standard as there are people using it.
that is true.
you're welcome.
chris
systems analyst, i.s.
solidworks/pdmworks 05
autocad 06
"simutaneous requirement" is understood in asme y14.5m-94 when there would be situation containing various positional tolerances referencing the same datums. this means that there is one (1) checking fixture for all the positional tolerances referencing the same datum in the same mode (mmc)rather than a separate fixture for each positonal tolerance.
i don't believe that many people know this so the designer in this case stipulated it.
the standard also states that if the designer required a separate requirement in one (1) positonal tolerances, then the designer would state "separate req". the one (1) positional tolerance noted must be checked or confirmed separately while the other ones would be checked or confirmed simutaneously.
hope this helps.
dd
thanks again dingy2!
i really appreciate your take on these questions.
so, although it is obviously a "simutaneous requirement", it was listed as clarification for the company.
chris
systems analyst, i.s.
solidworks/pdmworks 05
autocad 06
by y14.5m multiple composite positional tolerance feature control frames (ptcf) by default create separate requirements even if the datums are in the same order. if there are 'n' ptcfs then there are 'n' separate requirements. for example, a four-hole pattern of .106 diameter holes controlled with a composite ptfcf utilizing a/b/c in the top line and a in the bottom line. next, consider if there were another pattern of, say, ten .250 diameter holes in the same part having its own ptfcf where a/b/c is also in the top line and a is in the bottom line.
by default, these two requirements are separate (the note separate is not needed) indicating that the two hole patterns are independant (and probably do not mate to the same part). if the ptfcfs were not composite but instead possessed a single line then the requirements would be simultaneous by default.
in the composite case, if you don't want the requirements to be separate, then the placement of the note simultaneous under either ptfcf overrides the separate default and makes the requirements simultaneous.
tunalover
tunalover:
your notification the simultaneous requirements are defaulted in groups of composite feature control frames kind of threw me as bit. i check the y14.5m - 94 standard 5.3.6.2 page 93 and you are partially correct.
simultaneous applications do apply to the top section of the composite feature control frames (pltzf) but not the bottom or the (frtzf). if you know of any other section which is more explicit to you thoughts, please let me know.
i learned something myself on this about the bottom sections of composite feature control frames and i have been training in this subject for 18 years.
dd
promoting, selling, recruiting and student posting
are not allowed in the forums.
(add stickiness to your site by linking to this professionally managed technical forum)
title: drafting standards,
description: drafting standards, gd&t & tolerance analysis technical support forum and mutual help system for engineering professionals. selling and recruiting forbidden.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
【转帖】straightnesflatness requiremen yang686526 American standards 0 2009-05-04 10:33 AM
【转帖】simultaneous requiremen yang686526 American standards 0 2009-04-29 10:00 PM
【转帖】simultaeous requirements yang686526 American standards 0 2009-04-29 09:59 PM


所有的时间均为北京时间。 现在的时间是 06:26 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多