几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量  


返回   几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量 » 三维空间:产品设计或CAX软件使用 » CAD设计 » 产品功能分析
用户名
密码
注册 帮助 会员 日历 银行 搜索 今日新帖 标记论坛为已读


回复
 
主题工具 搜索本主题 显示模式
旧 2009-09-07, 05:08 PM   #1
huangyhg
超级版主
 
huangyhg的头像
 
注册日期: 04-03
帖子: 18592
精华: 36
现金: 249466 标准币
资产: 1080358888 标准币
huangyhg 向着好的方向发展
默认 bridge deck removal falsework

bridge deck removal & falsework
we are a contractor on a small bridge project which requires a 7" bridge deck slab to be removed & replaced between the existing cast-in-place girders.the bid design shows a temporary support structure at mid span of these existing girders with no stated bearing requirement.my falsework engineer has stated that we do not require a support at mid span due to the fact that the new deck is similar to the replaced one and that if it supported the old deck they will support the new deck.we have asked the designer to provide us with the bearing requirements for these supports and they have not been provided after 5 weeks and repeated requests.what is our next step?
check out our whitepaper library.
it took me a minute to understand the problem, but i beleive you are saying the falsework shown on the bid documents was to support the girders and not the wet concrete for the deck slab.
i assume the bridge is closed to traffic for this work and we can ignore live load considerations.
if my assumptions above are correct, then the designer is simply asking for these existing cast-in-place girders to be shored during the replacement of the deck slab. if the girders are shored at midspan, much less stress will be put into them from the wet concrete for the new deck slab.
after the concrete deck has cured, the shoring can be removed and much more composite capacity will remain for the live load than if the shoring did not occur. even if the original girders were not shored during construction of the original deck, by shoring for the replacement, the live load capacity can be improved somewhat.
the shoring also prevents excessive deflections at midspan which could also have been a design consideration.
i hope your bid price included enough for the shoring, and the shoring should be designed to support the weight of the wet concrete, reinforcing, forms, screeding equipment etc...
the shored girders act as a two-span continuous beam so make sure the reaction used for the design of the shoring towers takes this effect into account.
good luck, and give us an update on the falsework used once it is designed.

what you have described sounds like an old-fashioned bridge design with deck girders. when the exisiting deck is removed you are weakening the load carrying capability of the girder. the reduced depth of the integral deck/girder lowers both the section modulus (strength) and moment of inertia (deflection) of the girder that remains. (as an analogy, think of what removing the top flange of a load carrying steel wide flange beam would to it's strength.)
recommendation: provide the temporary support sturcture that you bid on. you have a lot at risk if something goes wrong.
as ttk states you need shoring otherwise it is possible that the beans will deflect during casting of the new deck slab and the final load bearing capacity of the bride will be affected. of course a design check may be able to show that the deflection is negligible.
i worked on a project like this before and we used twin steel plate girders supported on the bridge piers with a central underslung supporting beam. this worked well but as it was a river barrage withe 43 spans we had good re-use of the steelwork. incidently even though we proved after a couple of spans that deflections were negligible the design consultant would not relax the requirement for a central support.
zambo
the bridge was probably origionaly designed with the assumption that the girders and slab were supported by falsework that was left in place until the slab concrete reached its design strength. when the falsework was removed the stress in the reinforcing steel in the bottom of the beams would be calculated using the slab as the compression flange. if you assume the slab is supported by the beams with out falsework, then the stresses would be calculted using only the top of the beam as the compression flange. this will result in much higher stresses.
even if the beams were not designed as composite, it may be that support is required because lateral support (of the deck) has been removed.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
bridge deck pouring sequence huangyhg 产品功能分析 0 2009-09-07 05:08 PM
bridge collapse in mn part 2 huangyhg 产品功能分析 0 2009-09-07 05:04 PM
bridge abutment design huangyhg 产品功能分析 0 2009-09-07 05:02 PM
basic masonry bridge building in developing countries huangyhg 产品功能分析 0 2009-09-07 02:39 PM
b roof deck vs c floor deck - for floor use huangyhg 产品功能分析 0 2009-09-07 02:07 PM


所有的时间均为北京时间。 现在的时间是 09:48 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多