默认 force around an opening

force around an opening
folks,
i have a situation for which i need a creative solution. what you see in the attachment is a leg of a tilt up panel, through which the owner needs to run a 10" dia. pipe for stormwater.
i am required to evaluate if he can do it, meaning provide some alternate way to transfer the forces around the opening and then down the foundation.
does anyone have a similar experience?
thanks
i would add a vertical wt each side of the opening to reinforce what is left of the concrete.
daveatkins
@dave,
thanks for the suggestion. i am trying to get some more understanding of how the force flow is achieved.
as in how does the force transfer from the concrete to the steel member, and then back into the concrete? i am essentially making up for the area of lost concrete, but how long does the
if the force is purely axial, you can just introduce a section of steel pipe, dry pack grouted fully around solid into an oversized hole. this, however, will not work in uplift without some re-jigging...
the crushing strenght of the tube also needs to be considered for annular deflection. you can use mining tunnel pipe deflection formulae for this purpose.
hope that helps!
cheers,
ys
b.eng (carleton)
working in new zealand, thinking of my snow covered home...
imho both you and the owner should know better. surely there is a better location for the pipe.
i would design the panel as an "l" shaped panel, attaching the edge to the next panel and transferring the force from the 2' leg to the adjacent panel, avoiding the issue here. i would make the 2' leg containing the 10" diameter hole an infill, non-bearing panel.
from my tilt-up design experience, it just looks to me that there will be too much reinforcing required and too little structural space to utilize, especially considering shear reinforcing too. i can see two layers of #5 at 4 to 6" on center with ties, even if the hole is not there.
mike mccann
mmc engineering
msquared, why the ties in the leg? are you saying the #5's with ties due to the hole, or before the hole? are the ties only there for shear forces?
i normally design tilt-up legs less than 600mm wide as mike suggests... i cannot speak for mike, however i would usually have two layers of d (or hd) 12 (or 16) bars with r6 stirrups at 150 crs. that's very similar to mike's sugggestion, except metric, and i would use them before the hole. with the hole i would be looking to do a specific check, however i would default to hokie's position if the column experienced anything other than simple compressive loading.
essentially you're treating the leg as a column. this has always been a point of annoyance for me: when is a tilt-up panel a wall, and when is it a column? i have never found a code that will draw a line between column vs. wall dimensions or aspect ratio, despite having looked for this guidance for a long time. i have always tried to treat any tilt up panel as a column if i believed the behaviour would be more likely to be column-like, or it it has a thickness to width ratio of less than 1/4.
and yes, the stirrups are for the shear capacity, but also for confinement. if you have a slender panel all around, then they are also to permit ductile plastic hinge formation at high seismic loads.
cheers,
ys
b.eng (carleton)
working in new zealand, thinking of my snow covered home...
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
flange brace force huangyhg 产品功能分析 0 2009-09-09 12:15 PM
cutting an opening in unreinforced cmu wall huangyhg 产品功能分析 0 2009-09-08 04:18 PM
crane opening detail in reinforced concrete slab huangyhg 产品功能分析 0 2009-09-08 02:36 PM
c.k.wang intermediate structural analysis huangyhg 产品功能分析 0 2009-09-07 05:58 PM
air force engineer huangyhg 精密机械 0 2009-09-05 10:16 PM


所有的时间均为北京时间。 现在的时间是 08:47 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多