几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量  


返回   几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量 » 三维空间:产品设计或CAX软件使用 » CAD设计 » 产品功能分析
用户名
密码
注册 帮助 会员 日历 银行 搜索 今日新帖 标记论坛为已读


回复
 
主题工具 搜索本主题 显示模式
旧 2009-09-15, 03:01 PM   #1
huangyhg
超级版主
 
huangyhg的头像
 
注册日期: 04-03
帖子: 18592
精华: 36
现金: 249466 标准币
资产: 1080358888 标准币
huangyhg 向着好的方向发展
默认 proper lateral bracing

proper lateral bracing
i have 2 questions regarding the lateral bracing of beams.

first, when can a concrete deck sitting on a beam be considered to adequately brace the beam laterally? i know you can put shear studs in the beam, which would obviously brace the top flange from lateral movement. if there are no shear studs, and the form work for the concrete pour was placed just below the top flange, can that layer of outside concrete really be considered to brace the beam? also, after years of service, there will most likely be spalling in some areas along this beam, which would make me think i would only want to consider a deck as a lateral support if the beam has shear studs, or the pour occured at some depth of the web. i don't think i would want to really on friction as a lateral brace either.
second, can you brace the beam with a strut to the adjacent beam? i would think that you shouldn't brace to a beam that also needs bracing, and then consider both beams adequately braced unless the bracing was not perpendicular to their webs. yet, i've seen this kind of bracing a lot under bridges.
i've looked in the asd 9th edition, and skimmed through the aisc 13th edition, and have yet to find any information regarding this. does anyone have a good resource?
thanks a lot for any input
find a job or post a job opening
in terms of a single strut bracing two sections which need bracing, it depends on the connection and what they are bracing against as to whether this works. if you are only bracing against lateral torsional buckling and have the single brace connected to both
does the concrete deck have a metal deck form as well? if so, when the deck is perpendicular to the beam, we consider it braced. when parallel, i consider it unbraced, unless other beams are framing into the top flange.
if the concrete slab is placed on formwork level with the bottom of the top flange, i think the top flange is well braced laterally.
i agree with gywnn. i cannot envision concrete on top of steel without shear studs. composite action saves so much steel it is unreal.
with the shear stids, lateral bracing of the top flange really becomes a non-issue. however, you still have to consider the bottom flange where negative moments occur over columns at any frames or cantilevers. intermediate purlins or diagonal struts back to the slab work well here when needed.
mike mccann
mccann engineering
take another look in your 13th edition manual->appendix 6.
for more info, try to get a copy of the yura/helwig aisc bracing seminar notes.
i consider the situation you describe as a continuously braced beam. i don't think it matters if the deck is perpendicular or parallel. according to salmon and johnson, it doesn't take much to brace a beam flange.
daveatkins
i've seen metal deck considered as lateral bracing when the metal deck was puddle welded to the beam at a specific spacing.
fwiw and slightly off topic:
imho: shear studs are cheap only above a certain threshold. it is my understanding that the stud welding equipment must be calibrated and tested every time it is moved to a new job site. this takes some time and expense. if you only have a few studs on a job, it may be cheaper to go with non-composite steel.
steel fabricators and erectors in my area (nebraska) tell me somewhere around 500 to 750 studs for a job is the break even point. if you have a project with a small mezzanine, for example, with say 10 beams, it is unlikely that using composite action will save enough steel to pay for the calibration and testing of the stud welding machine.
jmho.
i agree with daveatkins: if there is a metal form deck attached to the beams then i would consider the beams fully braced.
also fwiw and also slightly off topic:
it is important to consider the use of a building before deciding to go with a composite system. i've seen several cases in industrial facilities where the original floor design used a composite system and due to changes in the processing they needed to cut new openings through the floor. this is very difficult to do with a composite floor.
thanks for the inputs.
this beam is an existing beam and did not have any shear studs installed. there was no metal deck form, and the concrete around the top flange has spalled along its length in various magnitudes. the fixed strut connection is a good point, that makes sense that it would be considered braced because for the beams to move it would have to bend the bracing.
one more quesion on shear studs. when does thermal growth/contraction become an issue on the studs? this beam is perpendicular to the length of the pier, and the deck on this side is very long with no expansion joints (~400 ft). if the expansion is not an issue, i would think another option would be to weld a plate to the top flange and bolting it to the underside of the deck.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
permanent truss bracing huangyhg 产品功能分析 0 2009-09-15 12:11 PM
lateral bracing for long span beam huangyhg 产品功能分析 0 2009-09-10 09:36 AM
lateral bracing for crane bays huangyhg 产品功能分析 0 2009-09-10 09:35 AM
lateral bracing for 100-foot tall free standing steel struc huangyhg 产品功能分析 0 2009-09-10 09:34 AM
bottom chord bracing for cold form trusses huangyhg 产品功能分析 0 2009-09-07 04:28 PM


所有的时间均为北京时间。 现在的时间是 10:56 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多