默认 5 overstress

5% overstress
i am working on a project that has a floor slab that was poured in the 1930's. i know the reinforcing size and spacing, but not the fc'. this is in a shower where the the slab slopes to a central drain (2 1/2" elev. change). the owner wants to use light weight concrete as a topping material. my question is: is it applicable to use the 5% overstress method? or do i make an assumption on the fc'? (coring a sample and breaking it, is out-of the question. i already asked).
check out our whitepaper library.
what do you mean about the 5% overstress method? how can you know the overstress if you do not know the f'c? politely tell your owner, light-weight fill is out of the question if we can't do some cores.
what was the design ll of the slab? what is the fy of the rebar?
some owners just don't understand how we do things i guess.
rc
all that is necessary for the triumph of evil is that good men do nothing.
edmund burke

the windsor probe method is a non-destructive method (uses an impact hammer) to determine compressive strength. its' not as accurate as a core, but is better than nothing.
also keep in mind that concrete continually gains compressive strength over time--and it's been a long time since the 1930's!
but i would guess the reinforcing is the weak link--probably 40 ksi steel, and maybe even less. and in the 1930's, they may have been using square bars, twisted bars, etc.
and yes, if you do not increase the loads by more than 5 percent, the code allows you to say ok without checking.
daveatkins
dave,
if there is a change in occupancy would the 5% still be allowed to apply? that is why i asked what the design ll was.
if it is not going to be a shower anymore, then the ll might be higher. also, if it was a shower for the last 75 years, i'd worry about corrosion of my steel.
just some thoughts.
rc
all that is necessary for the triumph of evil is that good men do nothing.
edmund burke
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭



所有的时间均为北京时间。 现在的时间是 12:56 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多