几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量  


返回   几何尺寸与公差论坛------致力于产品几何量公差标准GD&T (GDT:ASME)|New GPS(ISO)研究/CAD设计/CAM加工/CMM测量 » 三维空间:产品设计或CAX软件使用 » CAD设计 » 产品功能分析
用户名
密码
注册 帮助 会员 日历 银行 搜索 今日新帖 标记论坛为已读


回复
 
主题工具 搜索本主题 显示模式
旧 2009-09-08, 05:07 PM   #1
huangyhg
超级版主
 
huangyhg的头像
 
注册日期: 04-03
帖子: 18592
精华: 36
现金: 249466 标准币
资产: 1080358888 标准币
huangyhg 向着好的方向发展
默认 demolition of 5-story reinforced concrete building

demolition of 5-story reinforced concrete building
i have a question about logistics and risk management with regards to demolition of a heavy industrial building in an urban setting.
we are about to demolish a 5-story reinforced concrete structure in an urban setting. it was once a factory building, and approx 12 bays on each floor were designed for heavy live loads (10" thick flat slabs with 30" dia. concrete columns and shear caps.
after removing everyting but the concrete structure, the demo contractor proposes to attack the conctete slabs with a hydraulic excavator with a universal processor (concrete cracking jaws) and another with a concrete pulverizer, and yet another with a demolition grapple.
the contractor's work plan proposes to work from the bottom up (since access to the top of the building will be logistically difficult. the plan states:
"the second floor slab will be removed in sections of 200 to 300 square feet between columns followed by the removal of the same quantity of slab directly above the section just removed. once the section of roof slab has been demolished, slab removal between the next columns will begin. once roof slab has been removed, exposed column will be demolished, starting from top down."
while i have studied engineering, i am a construction program manager--not a practicing structural engineer. i am acting as the owner's rep, and my experience with demolition work is limited. this project appears to be one of the more challenging jobs that this demo contractor has undertaken.
won't removing the lower slabs destabilize the columns? it sounds spooky to me.
i am concerned and would appreciate any helpful advice from anyone experienced in such matters. we are in the hazmat abatement and interior demolition stage. the demolition specs don't require a formal submittal of an engineered demolition plan.
check out our whitepaper library.
demolishing the slabs is ok, but the problems will start once the main beams between the columns are removed. there will be a loss of strength in the frame and re-alignment of the load path, is this predicted? in most buildings the outside wall and frame of the building is the stiffest part, so it's normal just to go in and chomp away at everything. with a designed industrial building, it may not be the same, it is designed as a internal structural system with little external wall action.
i would remove the slabs, walls and leave the beams, on all levels, then from the top, design the selected beams for plastic structural failure, to become pinned at the joints and midspan. this will still tie the columns together.
i would get a structural engineer to look at it. most cities require some sort of demolition plan - and this to ensure that adjacent properties are not put at risk.
why are you involved with the demolition? the contractor is the 'expert' in construction and the manner of undertaking the work should be determined by him. the more you get involved, the more liability you assume. as a caution, with the original useage, the concrete could be well reinforced and detailed with liberal redundancy. is the building designed for seismic, too?
his approach appears to be reasonable; he might have to cable some of the columns to provide lateral support assuming that these elements have been removed. what sort of insurance does the contractor have and what is his experience.
you mentoned that it's in an urban setting. how much 'space' does he have around the perimeter?
thanks to all for your responses. i agree with dik & jae in the sense that i don't want to take on liability, but as the construction program manager, the client still looks to my firm to help steer them away from trouble. i certainly don't want anyone to get hurt. i'd prefer to have a demo engineer involved, and we might go that route, but we will likely face a change order (maybe it's a price we have to pay), since the bid docs don't require it.
we are surrounded by roads, parking lots and the backyards of some old, historical homes that are ripe for renovation, but currently unoccupied. there is a courthouse on the other side of a 4-lane road.
rtmote--thanks for the structural advice. sounds reasonable. i will look at the framing plans to see if i can discern some main beams in the flat slabs. as long as they retain a section of slab along the grid lines, sounds like it might work.
the contractor has typical insurance (commercial general liability and commecial umbrella liability ($2m per ocurrence and $4m aggregate.)

your client doesn't want to get involved, either... you might want to undertake a pre-demolition damage report for the surrounding buildings... removing a mass may cause some 'springing up' of the adjacent soil. cutting away the slabs results in a redistribution of stiffness...
dik
the pre-demo property survey sounds like a great idea. i'll take lots of photos.
are there beams in this slab? the mention of column capitals seems to indicate flat slabs and therefore rtmotes comments about beams would not be applicable.
if this is indeed a flat slab then i would advise only a top down approach, who knows what will happen with the vibration of machinery e.t.c.
i fail to understand how acces to the upper levels would be easier once the bottom floors are removed?
the use of a demolition engineer should not be seen as optional, the price will be negligible compared to the project, also if something does happen then you are the most knowledgible party involved in the decision making and could therefore be held liable.
merry christmas
csd
as mentioned above i definately would get a consultant involved if the is any doubt based on the contractors experience. i've seen two reinforced concrete building demolition jobs go wrong in a flash.
here is one of several companies that do consulting work on such jobs.
sounds like a job for those crews that come in with shaped charges, detonator cord, etc. is it called implosive demolition? i've seen pictures of buildings that fall in on themselves with minimal disturbance to nearby structures.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
cracks on reinforced concrete dams huangyhg 产品功能分析 0 2009-09-08 02:30 PM
concrete sampling guidlines huangyhg 产品功能分析 0 2009-09-08 12:34 PM
concrete mix= reinfocing for exterior composit deck huangyhg 产品功能分析 0 2009-09-08 12:19 PM
chapter 4 preliminary design properties of concrete huangyhg 产品功能分析 0 2009-09-07 11:23 PM
32 story building framed with lightweight concrete huangyhg 产品功能分析 0 2009-09-07 08:40 AM


所有的时间均为北京时间。 现在的时间是 06:41 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多