默认 rc shear keys in building structures

rc shear keys in building structures
all,
i'm currently reviewing structural drawings for a code compliance check and the rc details indicate a 'shear key' at the interfaces between floor slabs, walls and columns etc. i understand that this is a standard way of detailing concrete pour breaks by north american practice. and for the purpose of design the joint is considered continuous for moment and shear transfer. this is a method in the uk that we are not familiar with. am i correct in understanding that the joint is effectively a smooth finish and effectively forms a separation joint with no aggregate interlock across the joint? if so does the joint not effectively become a hinge since the only thing continuous across the joint is the rebar.
any comments would be appreciated.
many thanks
hannis

a sear key is simply a "notch" in the concrete. typical aplication would be a joint between a wall and a footing. your the footing first with a piece of wood in the center of were the wall will be. this 2x4 piece of wood is removed and when the wall is poured it will "key" into the void providing shear resistance. the key does not provide moment resistance. that must be provided( and designed) by steel passing thru the joint.
i find it hard to belive this method is not common in the uk. what would you do instead?
the joint isn't treated as a hinge. the top steel and bottom steel are continuous through the construction joint. the key, known as a shear key, is responsible for carrying the shear through the joint. since the bottom steel is continuous and concrete isn't designed to act in tension, the steel will still carry the required tension. the top of the beam will be in compression, and the concrete will still act the same. the beam is still a working beam, even with the construction joint. having said that, most engineers require the joint to be at a 1/3 point of the beam, where neither the moment nor the shear is at a maximum.
question:
not being structural in expertise, i have seen it done two ways in pits within the confines of a plant where the floor was poured then the walls later. one with the 2 x 4 key and bent bars from the floor and with bent bars only without the key. is the method without the key acceptable practice? there is no soil swelling or anything against the walls.
the use of a shear key at the interface of a wall and a footing or a column and a slab seems to be a carryover from unreinforced concrete (residential) construction. it seems redundant in reinforced concrete where reinforcing crosses the joint. in environmental structures where a waterstop is required at the joint, a shear key can make the construction a real pain.
the use of whether a shear key is necessary can be determined by the amount of shear to be transfered across the joint. it has been the practice of many engineers in the us to just use shear keys at all joints.
additional dowels crossing the joint may also be used to transfer the shear using the shear friction concept defined by aci.
aci 318-02, 6.4.4 requires construction joints in structural floors to be located in the middle third of the span. the commentary states that "when shear due to gravity load is not significant, as is usually the case in the middle of the span for flexural
tfl the answer to your question is that in the uk the surface of the concrete would have the laitence removed to expose the aggregate thereby ensuring the joint integrity. hannis appears to be asking whether the prescence of the shear keys means that the laitence does not need to be removed and therefore the joint has a smooth finish. this seems unlikely to me as if rebar is passing through the joint i would expect the joint to be formed so as to ensure that there will not be rebar corrosion.
zambo
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
pre-engineered metal building engineer sse or ser huangyhg 产品功能分析 0 2009-09-15 02:08 PM
multistory wood shear walls, overturning and uplif huangyhg 产品功能分析 0 2009-09-10 03:29 PM
can i count on shear-friction capacity of the reinforcemen huangyhg 产品功能分析 0 2009-09-07 10:22 PM
block shear vs. shear rupture at connections huangyhg 产品功能分析 0 2009-09-07 03:57 PM
beam shear huangyhg 产品功能分析 0 2009-09-07 03:01 PM


所有的时间均为北京时间。 现在的时间是 07:49 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多