默认 control joints in cmu shear walls

control joints in cmu shear walls
help!!!
i have a 48'x72', three story masonry structure that needs control joints. the wall openings set by the architect determined my shear walls locations. can you place a control joint in a shear wall, say at the neutral axis or to heck with it and not place any joints letting the building crack?
tia

i would say that if you put a control joint in a shear wall, then you just made two shear walls from one. i would design and detail them as two since they are seperated by the joint. the joint will allow slip between the walls causing them to act as two rather than one.
ucfse -
the way i've always approached it is if the horizontal reinforcing is running continuously through the joint, then i treat it as a continuation of the adjacent wall. however, if the reinforcing is stopped, then i treat it as you have stated.
"the way i've always approached it is if the horizontal reinforcing is running continuously through the joint, then i treat it as a continuation of the adjacent wall. however, if the reinforcing is stopped, then i treat it as you have stated."
if the reinforcement runs continuously through the joint, then how do you have a joint?
i think that ucfse is right and you have two walls beside each other. it takes a very strong vertical shear connection to force the two walls to act compositely. by the way, the neutral axis is the location with the most shear -- think vq/i...
good luck.
dbd
however, your bond beam carries across the cj to resist the chord forces. what happens to this element as the building begins to expand and contract?
i have always designed shear walls the way that ucfse has mentioned. the cj will prevent the transfer of shear across the joint. the top bond beam helps to distribute the horizontal in-plane load to the various wall panells. regarding bond beams, if the bond beam is required for strength, as in the case of a diaphragm chord, it must be continuous across a cj. the amount of steel in the beam compared to the cross sectional area of the wall is not enough to prevent the cj from working. one chord will be in tension with the rebar carrying the tension, so the bond bema will probably have some cracking any way. if the building is really large, you would need a joint through the entire structure to relieve the expansion/contraction forces.
bond beams for crack control should not be continuous across the cj. cj's are recommended to encourage cracking in contoleed locations when cmu shrinks, so you can prevent water from penetrating the wall. with brick, the you need joints to allow for expansion of the brick due to moisture absorbtion by the brick. if you don't have them in brick, you will probably see distress, especially at corners and any offsets as the brick grows. a brick parapet without joints can suffer a lot of distress. joints in a brick veneer and a cmu backup should line up.
it really depends whether the joint is vertical or horizontal. if it is a true shear wall, there are no out-of-plane forces. if the joint is horizontal you may see slipping between two block courses. if the joint is vertical it most likely will not slip.
motorcity,
please explain "most likely"fff">?
str04
for the two shearwalls separated by a vertical joint, i can see them slipping out of plane in two ways.
first, if the load is large enough, it could cause the two walls to act like a hinge and fold at the construction joint (or fail from the flexure whichever comes first).
also, if there is a significant seismic load, it could cause the walls to heave out of plane.
not being familiar with the design parameters, i made an educated guess that neither of those events is likely to occur. but of course it depends on your seismic and wind loads. hope that clarified my previous response.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
concrete tanks - vertical construction joints in walls huangyhg 产品功能分析 0 2009-09-08 12:55 PM
can i count on shear-friction capacity of the reinforcemen huangyhg 产品功能分析 0 2009-09-07 10:22 PM
block shear vs. shear rupture at connections huangyhg 产品功能分析 0 2009-09-07 03:57 PM
beam shear huangyhg 产品功能分析 0 2009-09-07 03:01 PM
beam shear in walls of below grade structure huangyhg 产品功能分析 0 2009-09-07 03:01 PM


所有的时间均为北京时间。 现在的时间是 05:31 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多