engineered shop drawings
this is a general question for practing structural engineers....do you require sealed shop drawings for all prefabriacted componets on a building you are the e.o.r.? i'm thinking of wooden trusses, timberframes ect. where does the architect fall in the scheme of things if they are required...what if this shop drawing review wasn't in the contract? thanks.
check out our whitepaper library.
we typically require signed and sealed calcs with the shop drawings. this is usually done as a performance spec. if this review wasn't in the contract and it is critical to the overall function of the structure... i would still want to review them, i wouldn't know how to go about requesting payment.
we require sealed shop drawings if we are eor, we do not require calc's with the submision. if we notice something we have a problem with, we phone. if someone asked me for my calc's with the shop drawing submission, i'd likely tell him to 'piss off', and if the requirement to 'submit calculations' was in the tender package i wouldn't participate.
as a plans examiner, i require the shop drawings to be sealed and submitted sometime before full plan approval is granted. in addition to examples given, i looking for steel connections, curtain wall designs, windows, etc.
don phillips
by the way the architect always falls out of harms way with respect to the eor. a question for the insurer lawyers no doubt, but is my experience. architects are all over the place. to give my opinion on the other part of the question, don't depend upon them (architects or definetly their insurers lawyers) to back you up.
connect-
are you talking about shops for items you design like the main structural steel?
why would you not want calcs for something that someone else is designing? ultimately, it is your responsibility if anything goes wrong since you are the eor.
we require calcs to review for everything we don't design in-house.
structuraleit.
the responsibility i understand, but i have never requested nor reviewed another engineers calculations as part of the shop drawing review process. the day you request calculations you may as well just have done the design yourself. we have had clarification requirements and subsequent changes in the submission phase. we will submitt our calculations at the request of building officials only. structural steel except for special connections we design the fabricator submitts sealed drawings we review the drawings ask for clarification as required. exactly what and how do you review the submitted calc's?
we don't review calcs for the steel (except for connection calcs).
i'll give a couple of examples.
1. for metal studs - we always write this as a performance spec. the engineer that designs them submits shops and calculations to us. we review the calcs for proper loading, proper intent (just because a metal stud is crossing a beam doesn't mean the beam was designed to clip back to it and cause weak axis bending). we also check for coordination between their calcs and drawings. if they have 4 different base connections at different jamb studs we check to make sure the capacity for the connection provided is greater than the reaction (you would be surprised how often this is not the case).
2. for stair shops - we again check for proper loading. we have got many stair shops where they cut the string at a kink and don't provide any reinforcement where the cut section is inadequate. again, check for coordination items, check connections to the main structure.
3. for curtain wall shops - we check for loadings, make sure the correct gcpi was used.
there are definitely things to review in the calcs
structuraleit,
if you review calcs yes '... there are definetly things to review ...', infact i would sugest that there is everything to review. you must then do the design for a second time. it would appear to me that you do a 'selective' review. what if you have missed an arithmatic error? by asking for calc's have you then implied that you will check all the cal's, or do you specify that you will check only certain calc's or components of the design?
i require sealed and signed shop drawings for engineered wood & cold-formed metal trusses, bar (open-web steel) joists, metal building framing.
i always get sealed and signed drawings for metal building framing.
i never get sealed and signed drawings for bar joists. i've tried in total futility to get them.
i sometimes get sealed and signed shop drawings for trusses. it depends on the fabricator. most provide the seal and signature if they provide trusses for commercial project. fabricators who do mostly residential rarely provide sealed and signed shop drawings.
yea, signed and sealed calcs. on everything. at least that's what my experience is.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
dots requiring pe stamps on shop drawings huangyhg 产品功能分析 0 2009-09-08 07:18 PM
copied cds as shop drawings huangyhg 产品功能分析 0 2009-09-08 01:56 PM
certify fabrication drawings huangyhg 产品功能分析 0 2009-09-07 11:17 PM
certification of shop drawings huangyhg 产品功能分析 0 2009-09-07 11:16 PM
cad files for shop drawings huangyhg 产品功能分析 0 2009-09-07 06:06 PM


所有的时间均为北京时间。 现在的时间是 05:07 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多